Timeline
2025
June 2025
Phase 1 construction begins – mobilization and initial site setup
Summer 2025
Demolition of existing golf course structures and cart paths
Summer 2025
Major excavation begins – removal of 150,000+ cubic yards of soil from western floodplain
Late Summer 2025
Riprap removal and installation of river crossing infrastructure
Early Fall 2025
Backwater channels and alcoves created in Phase 1 area
Fall 2025
First major plantings – native plants installed in western floodplain
Late Fall 2025
Seeding and mulching of disturbed upland areas
Winter 2025-26
Natural establishment period as plants take root
2026
Spring 2026
First growing season monitoring and adaptive management
Early Summer 2026
Phase 2 site preparation and eastern area mobilization
Summer 2026
New pedestrian bridge construction – 260-foot span installation
Summer 2026
Phase 2 excavation of eastern floodplain and remaining areas
Fall 2026
Final revegetation and habitat feature installation – native plants installed in eastern floodplain
Late Fall 2026
Trail network and signage installation
Winter 2026-27
System integration and final stabilization
2027
Spring 2027
Major project construction completed – all areas accessible to public
Early Summer 2027
Minor excavation to connect river flows to newly restored areas
Fall 2027
Minor plantings
Fall 2027
Completion of Project construction